Complete a
Request for Water Line Location
- Applicant
will be notified with rough estimate of distance and
cost
- Pay DPW
$40.00 for a detailed cost estimate (will be
credited to cost of project)
- Enter into a
Line Extension Agreement with DPW
- Review DPW
"Special Provisions"
- Pay the
total due
DPW as shown on the Cost Estimate
- Provide
all easement documentation w/ easements granted to
DPW
- DPW will
apply for all state agency approvals (ADEQ & ACC)
- DPW will
notify applicant when approvals have been received
- Applicant
will select contractor and schedule pre-construction
meeting
- Give DPW
performance bond or cashier's check for the total
estimated cost of project
- Give DPW
construction schedule for scheduling all on-site
inspections
- Begin
installation of the new water line
- When
complete, call for final DPW inspection
- Engineering
firm will certify the line
- DPW will
apply for and receive Approval to Operate the Line
from ADEQ
- The
accounting for the project will be done to determine
if a refund is due applicant
- Applicant
will pay DPW any outstanding balance, or DPW will
issue refund to Applicant
- DPW will
accept line when all of the above is complete
- Meter may be
purchased when all of the above is complete
(PLEASE NOTE:
NO METER WILL BE ISSUED UNTIL THE ACCOUNTING IS COMPLETE
AND DPW HAS ACCEPTED THE LINE) |